Outapi water treatment construction progressing well

Outapi water treatment construction progressing well

Maria David

SIGNIFICANT progress is underway on the ambitious Outapi Water Treatment Plant (WTP) Extension and Upgrade Project, poised to more than double the region’s water capacity and ensure a reliable supply for years to come.

The initiative directly addresses the escalating water demands driven by rapid urbanization and population growth in Outapi Town and its surrounding communities within the Omusati Region.

NamWater spokesperson Lot Ndamanomhata indicated that for over two decades, the existing Outapi WTP, commissioned in 2001, has been a vital water source.


However, Ndamanomhata said that with the region’s increasing needs, the plant has reached its operational limits.

“The project is a strategic response to rising demand caused by urbanization and population growth,” he said.

He added that this upgrade will more than double the current capacity — from 180 cubic metres per hour to 438 cubic metres per hour — ensuring a reliable and sustainable water supply for the years ahead.

Ndamanomhata indicated that the project will be completed at an amount of N$141.8 million, with a construction timeline of 16 months.

He said that this project is being delivered through the professional partnership between China Jiangxi International and Homefin Properties Joint Venture, combining international experience and local expertise to ensure high-quality results.

“At NamWater, we are committed to delivering on our promise of Water for All, Forever,” he added.

He stressed that the Outapi WTP upgrade is not just a construction project — it is an investment in the health, prosperity, and future of the Omusati Region.