Ogongo – Oshakati Pipeline replacement and ancillary works to start soon

Ogongo – Oshakati Pipeline replacement and ancillary works to start soon

Maria David

NAMIBIA Water Corporation (NamWater) has reached a significant milestone in national water infrastructure with the signing of contracts for the construction of the Ogongo–Oshakati Pipeline Replacement and Ancillary Works.

The entire project, valued at close to N$240 million, includes a new 53-kilometre pipeline to replace the ageing asbestos-cement pipeline, allowing for higher pressures to meet the region’s future water demands.

NamWater Chief Executive Officer Abraham Nehemia said they are dedicated to delivering sustainable water solutions for both rural and urban communities. Nehemia made the remarks during the contract signing ceremony held in Windhoek on Friday, emphasizing that by addressing these critical pipeline issues, they are securing water access for generations to come. With government and contractor support, NamWater is ensuring a water-secure future for Northern Namibia.

He indicated that this project underscores NamWater’s commitment to securing a reliable water supply for Northern Namibia to support future demand growth and economic development.

He emphasized the urgency of this project, extending appreciation to the government for its support through the Namibia Water Sector Support Programme 1 (NWSSP 1).

“This pipeline replacement is a strategic investment in water security for the region. The existing pipeline, built in 1978, has served us well, but its deteriorated state has led to frequent breaks, disrupting water supply,” he said.

He added that this project reaffirms NamWater’s commitment to providing sustainable and reliable infrastructure for our communities.

Following extensive due diligence, NamWater identified that sections of the pipeline, particularly the Class 6 segment between chainage 35 km and 52 km, have deteriorated significantly, jeopardizing water supply security.

Frequent breaks along the most vulnerable 15-kilometre stretch from the Onambira off-take to Oshakati have required NamWater to limit pipeline pressure to 1.8 bars, reducing supply capacity and restricting the pipeline from meeting projected demand for FY2030/31.

In response, NamWater’s Civil Engineering Design Team developed a comprehensive replacement plan. The bidding process commenced on 15 January 2024 and closed on 22 March 2024, awarding contracts for each segment to; Part A: Ogongo Pump Station to Oshikuku transition point (19.7 km), awarded to China Gezhouba Group Company Ltd for N$88 million; Part B: Oshikuku to Onangombe (14.0 km), awarded to China Jiangxi Economic and Technical International Corporation Ltd for N$69.6 million; and Part C: Onangombe to Oshakati connection (17.9 km), awarded to New Era Investment Pty Ltd JV CCCC Origin Water Construction Group Co. Ltd for N$79.6 million.

The contractors have committed to delivering high-quality work within the 12-month project timeline.

Lijie Li of China Gezhouba Group expressed pride in supporting Namibia’s water sector, pledging to “deliver quality work that meets the nation’s expectations.” Yang Deng of China Jiangxi Corporation and Rong Ma from New Era Investment JV CCCC similarly committed to the project’s urgency and high standards.