IN the fourth quarter (Q4) of 2023, B2Gold’s Otjikoto Mine set a new production record, yielding an impressive 81,111 ounces of gold.
According to the Chamber of Mines, the Otjikoto Mine demonstrated outstanding performance in 2023, producing a total of 208,598 ounces of gold for the full year. This achievement aligns closely with the upper limit of the projected guidance range, set at 190,000 to 210,000 ounces.
The Chamber of Mines attributed this success to the sustained and reliable production from both the Wolfshag underground mine and the Otjikoto open-pit mine.

“Gold production at Otjikoto is expected to be relatively consistent throughout 2024 with a gold production guidance set between 180,000 to 200,000 ounces of gold,” the Chamber of Mines added.
The Chamber of Mines disclosed the 2024 plans for the Otjikoto Mine, outlining the intention to process a cumulative 3.4 million tonnes of ore. The anticipated average grade is 1.77 g/t gold, and the mining operation aims for a noteworthy process gold recovery rate of 98.0%.
“Processed ore will be sourced from the Otjikoto pit and the Wolfshag underground mine, supplemented by existing medium and high-grade ore stockpiles. For 2025, gold production is expected to be between 180,000 and 200,000 ounces, similar to 2024,” the Chamber of Mines added.
The Chamber of Mines clarified that ore extraction in 2024 will predominantly come from Phase 5 of the Otjikoto open pit and the Wolfshag underground mine. They further indicated that the mill throughput, gold grade processed, and gold recoveries are projected to remain consistent with the levels observed in 2024.
The Chamber of Mines additionally disclosed encouraging exploration drilling outcomes from a recently explored region situated approximately 3 kilometres south of the Otjikoto Mine Phase 5 open pit, identified as the Antelope deposit.
“Discovered in 2022 through deep drill testing, the deposit consists of up to three separate mineralized structures, showing promising characteristics for potential future development. A total of £9 million is budgeted for exploration at Otjikoto in 2024, the largest program since the definition of the Wolfshag discovery in 2012,” the Chamber of Mines explained.
The focus of the exploration program, the Chamber of Mines added, will be drilling the recently discovered Antelope deposit, with a total of 39,000 m of drilling planned.
“As part of the mine’s operational strategy, open-pit mining operations are scheduled to ramp down throughout 2024 and conclude in 2025, while underground mining operations at Wolfshag will continue through 2026. Exploration results received to date indicate the potential to extend underground production at Otjikoto past 2026, supplementing the processing operations which will continue until 2031 when economically viable stockpiles are forecast to be exhausted,” the Chamber of Mines explained.