Maria David
A total of 160 ervens in Onguta have been officially connected to a new sewer pump station.
The project, which cost about N$7.5 million, was completed in June of this year.
Rudhi Wanamene, the owner of Wana Engineering Consulting, explained that they have completed the reticulation where houses are connected.
Wanamene stated, “The sewer waste from the houses will be reticulated all the way to the sewer pump station. The first manhole is called the junction where water comes in and it is screened. From the manhole, it enters into the sewer pump station.”
He added that the water is then pumped into the oxidation ponds.
Wanamene emphasized that the system is automatic, pumping directly to the main pump.
Ondangwa Town spokesperson Petrina Shitalangaho-Mutikisha mentioned that they have successfully provided full water and sewer services to 178 ervens, which have been occupied.
“A total of 102 ervens in the same area have partial services for water, sewer, and electricity,” she said.
Meanwhile, Shitalangaho-Mutikisha stated that during the current financial year, the council plans to upgrade the Onguta road to Bitumen standard.