THE Ministry of Agriculture, Water, and Land Reform intends to secure sufficient budget allocation in the 2021/2022 financial year to complete the Regional Agriculture head office that was abandoned in Eenhana
The ministry issued a tender to construct the office building in 2014 for N$ 34 million to Spes Bona Construction and Renovations CC.
However, in 2017, the contractor absconded and left the construction site due to the inability to continue due to the company experiencing financial problems.
The Deputy Director for Public Relations of the agriculture ministry, Chrispin Matongela said for the past three financial years, most of the ministerial projects were affected by the exorbitant charges and penalties arising from the construction of the Neckartal Dam.

“There are no payment disputes neither outstanding nor unpaid invoices at the ministry,” he said.
The agriculture minister, Calle Schlettwein during a recent visit to the site where the ministry was supposed to be accommodated, expressed disappointment over contractors failing to complete government tenders.
Schlettwein said the government will no longer tolerate companies abandoning projects as this is wasting taxpayer’s money.
He indicated that the building was supposed to be completed four years ago.
Schlettwein said that the agriculture ministry has embarked on a project with the Ministry of Works and Transport to make a list of unfinished capital projects.
“We have now decided to ensure that all salvageable capital projects are completed as the government cannot allow that taxpayers’ money going to waste,” he said during the visit.