Eba Kandovazu
THE Supreme court will tomorrow morning deliver a ruling on whether or not the High court misdirected itself by nullifying a N$211 million contract for a Chinese company to upgrade the Ondangwa airport, now known as the Toivo ya Toivo airport.
The Chinese contractor, China State Construction Engineering Corporation(China State), under the administration of suspended former Namibia Airport Company (NAC) CEO Tamer El-Kallawi, won the tender to upgrade the airport in 2014.
The board at the time, according to Lot Haifidi, who was appointed acting CEO in 2017, acted irregularly.
Haifidi at the time of the High court matter suggested in an affidavit that the contract was irregular and did not appropriately follow the tender processes.

El-Kallawi was suspended together with the head of NAC Engineering and Projects department, Courage Silombela.
The company’s procurement policy had not been followed, the new board also stated.
It is reported that Project engineers at Aurecon Namibia in 2016 projected that the upgrade at the airport would cost a mere N$169.9 million.
As such, it was unclear to the current board how the N$211 million for the upgrade by China State was arrived at.
China State at the time on its part argued that constructions had already begun and that with the delay, money was being lost.